This page provides guidelines about how to perform the development management, monitoring and control.
High Level Supervision Meetings
- Every two weeks will be performed a High Level Supervision Meeting
- All development component leaders have to participate on it.
- All development component leaders have to update beforehand the complete % field of the component tickets (tickets labelled with Component) they lead
- The values will be later on available at the follow-up Google spreadsheet for monitoring the evolution
- The status updates will be very brief (2 min. per component). If some component needs extra discussion specific meetings will be arranged with the interested stakeholders.
Here you can find the old spreadsheet.