Discussion
-
Yazid
2016-07-07- status: Not-Started --> Ongoing
- complete: 0 --> 5
- milestone: M30 --> M22
-
Yazid
2016-07-07This component has taken a slight delay because of the different amendments that have been applied to architecture.
-
Ruben de Juan
2016-07-20- labels: DCF, Component, LL_CEP, Partner_Linagora --> DCF, LL_CEP, Partner_Linagora, Old_Component
-
Ruben de Juan
2016-07-20- labels: DCF, LL_CEP, Partner_Linagora, Old_Component --> DCF, LL_CEP, Partner_Linagora, Obsolete
-
Ruben de Juan
2016-07-20- labels: DCF, LL_CEP, Partner_Linagora, Obsolete --> DCF, LL_CEP, Partner_Linagora, Old_Component
-
Yazid
2016-07-21- complete: 5 --> 10
-
Yazid
2016-09-19- complete: 10 --> 60
- is_usable: False --> True
- milestone: M22 --> M27